* Operations Authorization – Install/Remove (OA-R) grants approval for a proponent to carry out any activity in the Canada-Nova Scotia offshore area related to the installation or removal of oil and gas facilities. * Operations Authorization – Production (OA-P) grants approval for a proponent to carry out any activity in the Canada-Nova Scotia offshore area related to oil and gas production. * Approval to Alter the Condition of a Well (ACW) is required to re-enter, workover, complete, recomplete, suspend or abandon a well or part of it. The application for an ACW is reviewed in conjunction with the operator’s application for an Operations Authorization – Drilling (OA-D) or Operations Authorization – Production (OA-P), as applicable.
Activity | Applicant | Date Submitted | Approval Status |
---|---|---|---|
Operations Authorization – Install/Remove - AMENDMENT |
Ovintiv Canada ULC (formerly Encana) |
26/04/21 |
Approved (13/08/21) |
Operations Authorization – Install/Remove - AMENDMENT |
Ovintiv Canada ULC (formerly Encana) |
20/08/20 |
Approved (11/09/20) |
Well Approval: Approval to Alter the Condition of a Well (Panuke H-08) |
Ovintiv Canada ULC (formerly Encana) |
26/08/20 |
Approved (09/09/20) |
Well Approval: Approval to Alter the Condition of a Well (Margaree E-70) |
Ovintiv Canada ULC (formerly Encana) |
26/08/20 |
Approved (09/09/20) |
Well Approval: Approval to Alter the Condition of a Well (Margaree F-70) |
Ovintiv Canada ULC (formerly Encana) |
26/08/20 |
Approved (09/09/20) |
Well Approval: Approval to Alter the Condition of a Well (MarCoh D-41) |
Ovintiv Canada ULC (formerly Encana) |
26/08/20 |
Approved (09/09/20) |
Well Approval: Approval to Alter the Condition of a Well (Panuke M-79A) |
Ovintiv Canada ULC (formerly Encana) |
26/08/20 |
Approved (09/09/20) |
Operations Authorization – Production - AMENDMENT |
Ovintiv Canada ULC (formerly Encana) |
20/08/20 |
Approved (09/09/20) |
Operations Authorization - Install/Remove |
Ovintiv Canada ULC (formerly Encana) |
03/03/20 |
Approved (03/07/20) |
Operations Authorization - Production - AMENDMENT |
Ovintiv Canada ULC (formerly Encana) |
27/01/20 | Approved (13/02/20) |
Well Approval: Approval to Alter the Condition of a Well (Margaree F-70)(Plug and abandonment phase) |
Ovintiv Canada ULC (formerly Encana) |
12/12/19 |
Approved (28/02/20) |
Well Approval: Approval to Alter the Condition of a Well (Panuke M-79A)(Plug and abandonment phase) |
Ovintiv Canada ULC (formerly Encana) |
12/12/19 |
Approved (28/02/20) |
Well Approval: Approval to Alter the Condition of a Well (Panuke H-08)(Plug and abandonment phase) |
Ovintiv Canada ULC (formerly Encana) |
12/12/19 |
Approved (28/02/20) |
Well Approval: Approval to Alter the Condition of a Well (Margaree F-70)(Plug and abandonment phase) |
Ovintiv Canada ULC (formerly Encana) |
12/12/19 |
Approved (28/02/20) |
Well Approval: Approval to Alter the Condition of a Well (MarCoh D-41)(Plug and abandonment phase) |
Ovintiv Canada ULC (formerly Encana) |
02/12/19 |
Approved (28/02/20) |
Well Approval: Approval to Alter the Condition of a Well (MarCoh D-41) (Injection phase) |
Encana Corporation |
07/08/19 |
Approved (19/08/19) |
Well Approval: Approval to Alter the Condition of a Well (Panuke M-79A) (Injection phase) |
Encana Corporation |
07/08/19 |
Approved (19/08/19) |
Well Approval: Approval to Alter the Condition of a Well (Margaree F-70) (Injection phase) |
Encana Corporation |
07/08/19 |
Approved (19/08/19) |
Well Approval: Approval to Alter the Condition of a Well (Panuke H-08) (Injection phase) |
Encana Corporation |
07/08/19 |
Approved (19/08/19) |
Operations Authorization - Production – AMENDMENT |
Encana Corporation |
27/06/19 |
Approved (02/08/19) |
Operations Authorization - Production - AMENDMENT |
Encana Corporation |
28/02/19 |
Approved (08/04/19) |
Operations Authorization - Production - AMENDMENT |
Encana Corporation |
14/06/18 |
Approved (19/09/18) |
Operations Authorization - Production - AMENDMENT |
Encana Corporation |
30/04/18 |
Approved (15/06/18) |
Well Approval: Approval to Alter the Condition of a Well (Panuke PI-1B) |
Encana Corporation |
30/04/18 |
Approved (15/06/18) |
Operations Authorization - Production - RENEWAL |
Encana Corporation |
31/05/17 |
Approved (31/07/17) |